Air-emissions permit application

Green Mountain AS data centre in Tinn, Norway

Latest document dated 12 Dec 2025, from NVE (Norwegian Water Resources and Energy Directorate). Official document

Location of the project in Europe. Grey dots: other projects in the index.
backup generators
12
MW of grid connection
112

The backup fleet in the filing

Each block is one generator set: 12 in all.

Timeline

Public documents for this project, and what our daily checks found.

  1. Air-emissions permit application

    NVE (Norwegian Water Resources and Energy Directorate). Official document

  2. Licence Display windows, objection deadlines and every amendment, with page references

The record

Standby Atlas recordNO-TELEMARK-TINN-GREENMOUNTAIN-RJU
Location
Tinn (Rjukan), Norway
Operator or project company
Green Mountain AS
Stage
Air-emissions permit application
Filing date
12 Dec 2025
IT load
Not stated in the filing
Grid connection
112 MW
Backup generators
12
Generator thermal input
Not stated in the filing
Engine makes named
Not named in the filing

Source: NVE (Norwegian Water Resources and Energy Directorate). Checked on 9 November 2026.

This record as JSON

What the licences add for this project

Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.

Follow new filings

Free Atom feeds, updated with each monthly release.