Environmental-authority opinion (MRAe)
Digital MRS5 data centre in Marseille, France
Latest document dated 4 Apr 2024, from Mission régionale d'autorité environnementale (MRAe). Official document
- backup generators
- 14
- MW of generator thermal input
- 103.2
The backup fleet in the filing
Timeline
Public documents for this project, and what our daily checks found.
- Environmental-authority opinion (MRAe)
Mission régionale d'autorité environnementale (MRAe). Official document
- Official document online at our check
Checked every day since 9 Nov 2026.
- Licence Display windows, objection deadlines and every amendment, with page references
The record
Standby Atlas recordFR-PACA-MARSEILLE-DIGITALREALTY-MRS5
- Location
- Marseille (2e arr., quartier de la Calade, Grand Port Maritime), France
- Operator or project company
- Digital MRS5
- Stage
- Environmental-authority opinion (MRAe)
- Filing date
- 4 Apr 2024
- IT load
- Not stated in the filing
- Grid connection
- Not stated in the filing
- Backup generators
- 14
- Generator thermal input
- 103.2 MW
- Engine makes named
- Not named in the filing
Source: Mission régionale d'autorité environnementale (MRAe). Checked on 9 November 2026.
What the licences add for this project
Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.
Other projects in France
- 114generatorsSNC Data Hills data centre in Aulnay-sous-Bois, FranceEnvironmental-authority opinion (MRAe), 12 Feb 2025
- 111generatorsMicrosoft 1985 Sàrl data centre in Petit-Landau / Hombourg, FranceEnvironmental-authority opinion (MRAe), 22 Jun 2026
- 74generatorsSAS PIPA-DC1 data centre in Blyes, FranceEnvironmental-authority opinion (MRAe), 13 Aug 2026
- 72generatorsInterxion France data centre in La Courneuve, FranceOther filing, 23 May 2025
- 69generatorsOVHcloud data centre in Gravelines, FranceEnvironmental-authority opinion (MRAe), 28 Oct 2025
- 62generatorsLCP FR DC1 data centre in Corbeil-Essonnes / Le Coudray-Montceaux, FranceEnvironmental-authority opinion (MRAe), 7 May 2025