Digital MRS5 data centre in Marseille, France

Latest document dated 4 Apr 2024, from Mission régionale d'autorité environnementale (MRAe). Official document

Location of the project in Europe. Grey dots: other projects in the index.
backup generators
14
MW of generator thermal input
103.2

The backup fleet in the filing

Each block is one generator set: 14 in all.

Timeline

Public documents for this project, and what our daily checks found.

  1. Environmental-authority opinion (MRAe)

    Mission régionale d'autorité environnementale (MRAe). Official document

  2. Official document online at our check

    Checked every day since 9 Nov 2026.

  3. Licence Display windows, objection deadlines and every amendment, with page references

The record

Standby Atlas recordFR-PACA-MARSEILLE-DIGITALREALTY-MRS5
Location
Marseille (2e arr., quartier de la Calade, Grand Port Maritime), France
Operator or project company
Digital MRS5
Stage
Environmental-authority opinion (MRAe)
Filing date
4 Apr 2024
IT load
Not stated in the filing
Grid connection
Not stated in the filing
Backup generators
14
Generator thermal input
103.2 MW
Engine makes named
Not named in the filing

Source: Mission régionale d'autorité environnementale (MRAe). Checked on 9 November 2026.

This record as JSON

What the licences add for this project

Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.

Follow new filings

Free Atom feeds, updated with each monthly release.