Free sample

Public notice: prior and construction authorisation

Data Riocaya, S.L.U. data centre in Badajoz, Spain

Latest document dated 15 Sep 2026, from Boletín Oficial del Estado. Official document

Location of the project in Europe. Grey dots: other projects in the index.
MW of grid connection
300

The backup fleet in the filing

The filing does not state how many generator sets there are.

Timeline

Public documents for this project, and what our daily checks found.

  1. Public notice: prior and construction authorisation

    Boletín Oficial del Estado. Official document

  2. Official document online at our check

    Checked every day since 9 Nov 2026.

  3. Licence Display windows, objection deadlines and every amendment, with page references

The record

Standby Atlas recordES-EX-BADAJOZ-NOSTRUM-EVERGREEN
Location
Badajoz, Spain
Operator or project company
Data Riocaya, S.L.U.
Stage
Public notice: prior and construction authorisation
Filing date
15 Sep 2026
IT load
Not stated in the filing
Grid connection
300 MW
Backup generators
Not stated in the filing
Generator thermal input
Not stated in the filing
Engine makes named
Not named in the filing

Source: Boletín Oficial del Estado. Checked on 9 November 2026.

This record as JSON

What the licences add for this project

Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.

Follow new filings

Free Atom feeds, updated with each monthly release.