Public notice: prior and construction authorisation
Ignis Data Alfa, S.L. data centre in Villalbilla, Spain
Latest document dated 6 Feb 2026, from Boletín Oficial del Estado. Official document
- MW of grid connection
- 181.6
The backup fleet in the filing
The filing does not state how many generator sets there are.
Timeline
Public documents for this project, and what our daily checks found.
- Public notice: prior and construction authorisation
Boletín Oficial del Estado. Official document
- Official document online at our check
Checked every day since 9 Nov 2026.
- Licence Display windows, objection deadlines and every amendment, with page references
The record
Standby Atlas recordES-MD-VILLALBILLA-IGNIS-BETAII
- Location
- Villalbilla, Spain
- Operator or project company
- Ignis Data Alfa, S.L.
- Stage
- Public notice: prior and construction authorisation
- Filing date
- 6 Feb 2026
- IT load
- Not stated in the filing
- Grid connection
- 181.6 MW
- Backup generators
- Not stated in the filing
- Generator thermal input
- Not stated in the filing
- Engine makes named
- Not named in the filing
Source: Boletín Oficial del Estado. Checked on 9 November 2026.
What the licences add for this project
Exact engine models, abatement, fuel storage and permitted hours in the Backup Fleet licence; the dated history of every filing; grid and on-site power; and, from February 2027, ownership graded by evidence. Or order this project as a dossier for €490.
Other projects in Spain
- —generatorsData Riocaya, S.L.U. data centre in Badajoz, SpainPublic notice: prior and construction authorisation, 15 Sep 2026
- —generatorsInterxion España, S.L. data centre in Madrid, SpainPublic notice: prior and construction authorisation, 12 Jan 2026
- —generatorsACS DC Infra La Puebla, S.L. data centre in La Puebla de Alfindén, SpainPublic notice: prior and construction authorisation, 22 Jul 2026
- —generatorsData-centre project in Aragon, SpainPublic notice: prior and construction authorisation, 9 Sep 2025